From site preparation to construction
The ceremony took place on Thursday, 12 November 2026, on the northern side of the site, overlooking the upper Niagara River. It marked the completion of the planning and site preparation phase and the transition to construction, entrusted to general contractor Deltera Contracting Inc., part of the Tridel Group of Companies.
Zee Hamid, Ontario’s Minister of Tourism, Culture and Gaming, attended the event alongside the project partners. Provincial MPP Sam Oosterhoff described the restoration of this landmark as a central component of the Destination Niagara Strategy, the Ontario government’s plan to position the region among the world’s leading tourism destinations.
A developer-operator partnership
Toronto Power Hotel Inc. brings together Society Developments, which is overseeing construction, and Pearle Hospitality, the Ontario-based hospitality group behind properties including Elora Mill Hotel & Spa. Pearle Hospitality will manage and operate the hotel when it opens.
The initial CAD 350 million investment is being financed entirely by the private sector. Niagara Parks will also receive annual rental payments under the lease agreement with the project company.
“Our ambition is to make Toronto Power one of the world’s great hotel destinations and redefine the way people experience Niagara Falls,” said Aaron Ciancone, President of Pearle Hospitality. “At Pearle, we build with purpose, and for generations.”
Brian McMullan, Vice President of Business Development and Partner at Society Developments, sees the arrival of the city’s first five-star hotel and spa as “a historic milestone that will redefine luxury tourism in the region”.
A development open to the public
Beyond the hotel itself, the development will include free public viewing areas, both indoors and outdoors, four to five restaurants and a spa designed as a destination for both wellbeing and social interaction. Several event spaces, an art gallery and a museum will complete the offering. The project is expected to create up to 900 jobs in the region.
Drew Wensley, CEO of MT Planners, highlighted the site’s integration into the Niagara Parks trail network, connecting Toronto Power with the parks, walkways and attractions along the Niagara River. “This project becomes much more than the restoration of an iconic building or the arrival of a remarkable new hotel,” he said.
The development complements other investments undertaken by Niagara Parks across its tourism assets, including the redevelopment of Journey Behind the Falls, one of Niagara Falls’ flagship attractions, scheduled for 2028.
Industrial heritage at the heart of the project
Designed by Canadian architect E.J. Lennox, the power station operated from 1906 until its decommissioning in 1974. It was designated a National Historic Site of Canada in 1983 and stands above the Canadian Horseshoe Falls in Queen Victoria Park.
MT Planners and +VG Architects, both of which participated in the initial visioning exercise for Niagara Falls’ former power stations, are supporting the project to preserve the building’s historic character.
“This is Niagara Parks’ mandate in action: protecting and promoting Niagara’s natural and cultural heritage while developing tourism,” said Graham Coveney, Chair of Niagara Parks.
For Mario Cimicata, President of Construction Management at Deltera Contracting Inc., bringing this unique site back to life represents “both an exciting construction challenge and a responsibility” that the company takes seriously.
Five years of planning and approvals
Niagara Parks launched a three-stage process to solicit private-sector proposals in autumn 2021. Pearle Hospitality was selected as the successful proponent in autumn 2023. The signing of a letter of intent initiated a due diligence phase involving a series of technical studies and heritage assessments.
In autumn 2024, the province authorised Niagara Parks, through an Order-in-Council, to enter into the redevelopment lease. In summer 2025, a cofferdam was installed in the upper Niagara River to enable construction work on the riverside of the building. Substantial completion is expected in 2029.
Investor perspective
Analysis – The financing structure illustrates a heritage redevelopment model in which the public-sector owner makes no capital contribution. The private operator finances the entire initial investment and pays rent in exchange for operating rights. The budget has increased significantly since the provincial approval in 2024, which referred to CAD 200 million, highlighting the substantial costs associated with restoring historic infrastructure in a river environment.
Analysis – The project forms part of the region’s gradual move upmarket, already evident in Hyatt’s opening of The Clayfield in Niagara-on-the-Lake, and comes against the backdrop of a Canadian hotel market where the hotel development pipeline reached record levels in the first quarter of 2026.
At a Glance by The Hospitality Tribune
Toronto Power Hotel breaks ground in Niagara Falls
CAD 350m (c. EUR 222m) private investment by Toronto Power Hotel Inc. (Society Developments and Pearle Hospitality)
Adaptive reuse of a 1906 E.J. Lennox power station, designated a National Historic Site of Canada in 1983
Niagara Falls’ first five-star hotel, to be operated by Pearle Hospitality
Four to five restaurants, spa, event venues, art gallery, museum and free public viewing areas
Up to 900 jobs; substantial completion expected in 2029